 Development
 Overhead Power Line (EIA)
 Tealing to Westfield OHL 400kV Upgrade (Reconductoring) Project
 Consultation
 ECU00005168
  Fife Council; Angus Council; Perth and Kinross Council
 Albert Muckley
 Scottish Hydro Electric Transmission Plc
 Inveralmond House, 200 Dunkeld Road, Perth, PH1 3AQ
 albert.muckley@sse.com
 LT384
 The Proposed Development consists of the upgrade of approximately 37 km of Overhead Line between tower 182 (west of Tealing Substation) and the licence boundary with Scottish Power Energy Networks (SPEN) OHL network (Westfield/Glenrothes) (mid span towers 66 and 65), to enable operation at 400kV.
 04 Jul 2024
 37.20
 275kV (existing) and 400kV (proposed)
 79.60