We proposal to construct a new Overhead Line (OHL) to connect the consented Glendye Wind Farm to the National Grid. The proposal is a single circuit 132 kV steel trident pole arrangement, supporting the OHL running over a distance of approximately 20 kilometres in length from the on-site substation at the consented Glendye Wind Farm to the existing Fetteresso substation, in Aberdeenshire
10 Oct 2025
20
13