Limekiln Wind Farm Section 36C Variation Application - Scoping 
        
        
    
    
 
                            
    
        
    
    
         Limekiln Wind Ltd are seeking to vary the existing consent for Limekiln Wind Farm to:
	Increase the height of all turbines to 149.9m;
	Reroute certain access tracks;
	Removal of one borrow pit;
	Increase the operational period from 25 years to 40 years; and 
	Relocate the construction compound and increase its size from (100m x 100m) to (150 x 100m).  
        
        
    
    
 
                            
    
        
    
    
         05 Mar 2021