 Development
 Wind Farm (Generating station of >50 < 100 MW Capacity )
 Bankend Rig III Wind Farm
 Consideration
 ECU00004516
  South Lanarkshire Council
 Chris Pepper
 TNEI Services Limited
 7th Floor, 80 St Vincent St, Glasgow, G2 5UB
 0141 428 3180
 chris.pepper@tneigroup.com
 Wilma Wilson
 Wilson Renewables III
 Carbieston House, Ayr, Ayrshire, KA6 5JU
 0141 428 3180
 wilma.wilson@wilsonrenewables.com
 15747
 Application for Section 36 consent for Bankend Rig III Onshore Wind Project (erection of 10 wind turbine generators with an installed generating capacity of up to 66 MW at a height of up to 250 m, with associated accesses, cabling, infrastructure and temporary infrastructure on land 4 km south of Dungavel, South Lanarkshire).
 23 Jan 2024
 66
 250
 10