Wind Farm (Generating station of >50 < 100 MW Capacity )
Bankend Rig III Wind Farm
ECU00004516
South Lanarkshire Council
Ryan Llewellyn
TNEI Services Limited
7th Floor, West One, Forth Banks, Newcastle, NE1 3PA
0191 2111412
ryan.llewellyn@tneigroup.com
Wilma Wilson
Wilson Renewables III
Carbieston House, Ayr, Ayrshire, KA6 5JU
0141 428 3180
wilma.wilson@wilsonrenewables.com
15747
Application for Section 36 consent for Bankend Rig III Onshore Wind Project (erection of 10 wind turbine generators with an installed generating capacity of up to 66 MW at a height of up to 250 m, with associated accesses, cabling, infrastructure and temporary infrastructure on land 4 km south of Dungavel, South Lanarkshire).
23 Jan 2024
21 Nov 2025
Consented
66
10