Overhead Power Line (EIA)
Melgarve Cluster Project - Cloiche and Dell Wind Farm Connections
LT419, LT218 and LT287
Main Application - Approx 7.0 km of 132 kV OHL double circuit L7 towers carrying Cloiche and Dell wind farm connections and ancillary development comprising two cable sealing end compounds, approx 7.3 km of 132 kV underground cable (UGC) commencing from the proposed Dell Wind Farm on site substation, approx 1.8 km of 132 kV UGC commencing from the proposed Cloiche Wind Farm on site substation, approx. 0.8 km of two 132 kV UGC running parallel to each other on approach into Melgarve substation, upgrades to existing access tracks, new permanent access tracks (including bridges) and new temporary access tracks, vegetation clearance and temporary working working measures/areas. The total length of the new transmission connection would be approximately 16.9 km in length (which includes approximately 9.9 km of UGC)
01 May 2024