Please Log in/Register to turn notification preferences on/off for this case.
 Scoping
 Wind Farm (Generating station of >50 < 100 MW Capacity )
 Balnespick Wind Farm
 Pre Application
 ECU00004904
  Highland Council
 All Contacts
 ITPEnergised
 4th Floor Centrum House, 108-114 Dundas Street, Edinburgh, Midlothian, EH3 5DQ
 info@itpenergised.com
 Julie Aitken
 Fred. Olsen Renewables
 julie.aitken@fredolsen.com
 Scoping Request for construction and operation of a windfarm and energy storage facility within The Highlands Council, of approximately 9 turbines with a tip height up to 200m. Anticipated generating capacity is 55.8 MW with additional 10 MW of battery storage making the Total anticipated capacity 65.8 MW
 18 Aug 2023
 65.80
 200
 9