 Development
 Battery Energy Storage System (EIA)
 Kinmuck Battery Energy Storage
 Application
 ECU00004907
  Aberdeenshire Council
 Pippa Gardner
 David Bell Planning Ltd
 David Bell Planning Ltf , 26 Alva Street , Edinburgh
 pippa.gardner@dbplanning.co.uk
 Pippa Gardner
 Kinmuck Energy Storage Limited
 c/o David Bell Planning Ltd, 26 Alva Street, Edinburgh, EH2 4PY
 07807528686
 pippa.gardner@dbplanning.co.uk
 Application to construct and operate BESS with installed capacity of up to 105MW with ancillary 275kv / 33kV grid substation and related structures and works including site access and landscaping.
 13 Sep 2023