Wind Farm (Generating station of >50 < 100 MW Capacity )
663896
The proposed Development will comprise up to nine wind turbines with maximum 200 m blade tip height. Associated infrastructure will include:
a means of access from the public road to the Site
turbine foundations
crane hard standings
transformer/switchgear housings located adjacent to turbines
internal access tracks (use of existing, upgrade of existing or new as required), watercourse crossings (upgrade of existing or new as required) and associated drainage
underground electrical cabling
permanent anemometer mast or LiDAR compound
temporary wind farm construction compound area, laydown areas and car parking
substation compound with a control building with closed-circuit television mast(s) and communication mast(s)
energy (battery) storage
borrow pit search areas
forestry works (if required).
Ancillary development will include:
Health and Safety and other directional site signage
aviation warning lighting to comply with Article 222 of the UK Air Navigation Order (ANO 2016)
proposals for habitat management and enhancements.
14 Mar 2025