 Scoping
 Wind Farm (Generating station of >100 <200 MW Capacity)
 Altnabreac Wind Farm
 Pre Application
 ECU00006038
  Highland Council
 Stewart Robson
 WSP
 7 Lochside View, Edinburgh Park, Edinburgh, Midlothian, EH12 9DH
 +44 131 344 2300
 stewart.robson@wsp.com
 Ryan Bissoonauth
 Altnabreac Wind Farm Limited
 altnabreacwindfarm@wind2.co.uk
 Up to 17 wind turbines, with a generating capacity up to 130 megawatts (MW) of electricity and a battery storage facility along with associated infrastructure including, access tracks, crane hardstandings, control building / substation, electrical cabling between turbines and the substation and a temporary construction compound.
 27 Nov 2024