Screening
 Battery Energy Storage System (Other Generating Station)
 Thorntonloch BESS
 Pre Application Complete
 ECU00006056
 East Lothian Council
 Paul Booth
 AAH Planning Consultants
 AAH Planning Consultants, 1 Bar Lane, york, YO1 6JU
 01904629258
 admin@aahplanning.com
 Ross Sandbach
 GPC Project 14 Ltd
 S36 APPLICATION FOR THE CONSTRUCTION AND OPERATION OF AN ENERGY GENERATING SYSTEM, WHICH WILL COMPRISE A BATTERY ENERGY STORAGE SYSTEM WHICH WILL STORE UP TO 150MW OF ENERGY, TOGETHER WITH ASSOCIATED INFRASTRUCTURE, SUBSTATION, SECURITY FENCING, CCTV, SECURITY LIGHTING AND LANDSCAPING
 16 Dec 2024
 27 Feb 2025
 Non-EIA