Overhead Power Line (Non-EIA)
LT505 Coire Mashie 400kV Substation - Reconfiguration of Beauly - Denny 400 kV Overhead Line
ECU00006315
Cairngorms National Park; Highland Council
Marta Ibanez Garcia
Scottish Hydro Electric Transmission Plc
10 Henderson Road, Inverness, IV1 1SN
marta.ibanezgarcia@sse.com
LT000505
The Proposed Development is required to facilitate the connection of a new proposed 400 kV substation to the National Grid. The new proposed 400 kV substation, referred to as Coire Mashie substation will be the subject of a separate planning application (and screening request) to The Highland Council by the Applicant.
12 Jan 2026
1150
60