Scoping
 Overhead Power Line (EIA)
 Peterhead to Kintore Overhead Line (OHL) 400 kV Upgrade (PKUP)
 Pre Application
 ECU00006379
 Leona Graves
 Scottish Hydro Electric Transmission Plc
 10 Henderson Road, Inverness, IV1 1SN
 leona.graves@sse.com
 Reconductoring of approximately 51 kilometres (km) of an existing 275 kilovolt (kV) overhead line (OHL), connecting substations between Peterhead and Kintore to enable operation at 400 kV, and approximately 12 km of existing 132 kV OHL connecting the existing Persley Tee to Persley Substation to enable operation at 275 kV.
 14 Apr 2026
 63000
 400 kV (51 km); 275 kV (12 km)