Overhead Power Line (EIA)
DWNO Reinforcement Project - Uprating of XX and XR Overhead Lines from 275kV to 400kV and ancillary works
ECU00006382
North Lanarkshire Council
Alan Graham
SP Transmission Plc
Land and Planning, 55 Fullarton Drive, Glasgow, G32 8FA
07552266171
a.graham@spenergynetworks.co.uk
ECU00006196
The application proposes the uprating of existing overhead lines (OHL) XX and XR routes from 275kV to 400kV. XX OHL runs between Easterhouse substation and Newarthill substation. While XR route runs between Newarthill substation and Wishaw substation. The uprating shall comprise replacement of existing conductors (overhead line wires), downleads, temporary accesses, tower foundation upgrades and tower strengthening.
Four new towers are proposed on XX route at Glenmavis where the proposed new OHL (WB route) connects to XX route. Two permanent towers and one temporary tower are proposed adjacent to Newarthill substation.
Ancillary development includes the following: extension to Wishaw substation comprising an extension of the existing substation platform, gantries, outdoor air insulated switch gear, gas insulated busbars, drainage and associated security boundary fence.
12 Jun 2026
31000
61.06